We are pleased to inform you that as of August 15, 2012, Morgan Executive Residences Towers 1, 2 and 3 overall accomplishment is 92.00%, 61.00% and 48% respectively. Towers 1, flushing and functionality test of plumbing fixtures, interior and exterior final painting works, waterproofing works, meter center works and installation of: kitchen cabinet and closet, lavatory and countertop is ongoing. Ceiling works at hallway lobby, preparation for testing of AC units, exterior painting works, waterproofing works and testing of fire pro piping is ongoing for Tower 2. For Tower 3, continuous work includes installation of pipes, sanitary water line, copper piping and riser, exterior painting works, waterproofing works and finishing of transformer vault room.
The project is on progress with accordance to its schedule |