Tuesday, January 22, 2013

Updated Developments as of January 2013 for McKinley Hill Fort Bonifacio and Forbes Town Center Global City


We are pleased to inform you that as of January 15,2013 8 Forbestown Road overall project accomplishment is 49.86% complete. Concreting works is already at 54th floor. Ongoing work includes rebar works, formwork's, fabrication of rebars, plastering works, spraycrete of wall partition, application of waterproofing and installation of : CHB wall, Pre-cast wall and drop walls. Installation of air duct for mechanical, pipe sleeving works for sanitary and fire protection and electrical roughing-ins is also on development.
The Project is on progress with accordance to its schedule.


We are pleased to inform you that as of january 15, 2013, Morgan Executive Residences Towers 1,2 and 3 overall accomplishment is 94.61%, 76.40% and 59.20% respectively. For tower 1 ongoing works includes flushing and functionality test of plumbing fixtures at 18th Floor - 22nd Floor (for completion), interior finishing works is on going at 22nd floor with minor finishing works to complete, preparation of BTO for roof deck under mechanical works and ongoing retouching and final painting at basement area.  Installation of main door jamb, KED, fixtures, and wires is ongoing for Tower2. For tower 3 on going works includes installation of riser, piping of EWT, waterproofing test of Toilet and Bath at 19th floor and paintinf works.
The project is on progress with accordance to its schedule.


We are pleased to inform you that as of January 13, 2103, the Stamford residences Tower 1,2 and 3 overall accomplishment is 100%, 99.89% and 99.89% respectively. Mechanical works for tower 1 includes testing of remaining units and preparation of BTO. For tTower 2 and 3 under mechanical works, controllers of Fans and bowers are subject for replacement due to change in specifications and schedule for turnover of electrical works is still waiting.

We are pleased to inform you that as of January 15,2013, the overall project accomplishment for Tuscany Private Estate Phase I, II, III is 98.67%, 98.22% and 87% respectively. For Phase I (Cluster 1,2 and 7), remaining works inlcude punch listing for mechanical and plumbing works. For Phase II (cluster 3 and 4), punchlsiting for plumbing and fire protection worksat basement area is ongoing. For phase 3 (Cluster 5 and 6), installation of mechanical equipment, plumbing fixtures and droppings is on going.




We are pleased to inform you that as of January 15,2013 The Venice Luxury Residences overall project accomplishment for Tower's A and B is 46.85% and 42.90% respectively. For Tower A nad B ongoing works includes preparation of upper roof deck, piping works at basement area and painting works at residential units 4th floor to 6th floor.
The project is on progress with accordance to its schedule.

Wednesday, September 5, 2012

Project Update As The Month of September 2012


We are pleased to inform you that as of August 15, 2012 8 Forbestown Road
overall project accomplishment is 38.69% complete. Concreting works is
already at 51st floor. Ongoing work includes rebar works, formworks,
fabrication of rebars, plastering works, spraycrete of wall partition,
application of waterproofing and installation of: CHB wall, Pre-cast wall
and drop walls. Installation of air duct for mechanical, pipe sleeving works
for sanitary and fire protection and electrical roughing-ins is also on
development.

The project is on progress with accordance to its schedule.
We are pleased to inform you that as of August 15, 2012, Morgan Executive
Residences Towers 1, 2 and 3 overall accomplishment is 92.00%, 61.00% and
48% respectively. Towers 1, flushing and functionality test of plumbing
fixtures, interior and exterior final painting works, waterproofing works,
meter center works and installation of: kitchen cabinet and closet, lavatory
and countertop is ongoing. Ceiling works at hallway lobby, preparation for
testing of AC units, exterior painting works, waterproofing works and
testing of fire pro piping is ongoing for Tower 2. For Tower 3, continuous
work includes installation of pipes, sanitary water line, copper piping and
riser, exterior painting works, waterproofing works and finishing of
transformer vault room.

The project is on progress with accordance to its schedule


We are pleased to inform you that as of August 15 2012, the overall project
accomplishment for Tuscany Private Estate Phase I, II and III is 95.00%,
79.00% and 42% respectively. For Phase I (Clusters 1,2 and 7) and Phase II
(Clusters 3 and 4), remaining works includes installation of refrigerant
pipes and plumbing fixtures, pressure test and wiring works. For Phase 3
(Clusters 5 and 6), installation of kitchen exhaust duct, branch line and
loop line, droppings and wiring works is ongoing.

We are pleased to inform you that as of August 15, 2012, The Bellagio Tower
III overall project accomplishment is 99.99% complete. Ongoing work includes
rectification of unit owners punchlist, painting works and testing and
commissioning of Passenger elevator. Testing and installation of remaining
electrical systems is substantially complete.



We are pleased to inform you that as of August 15, 2012, The Stamford
Executive Residences Towers I, II and III overall accomplishment is 99.95%,
99.71% and 97.50% respectively. For Tower 1, remaining works includes
testing of remaining blowers and including DPSC. Wiring and installation of
blowers and turbo fan is ongoing for Tower 2 while basement 1, roof deck
area and EE room is for turnover also. Interior painting works, interior
finishing works, finishing of EE rooms prior to turnover, piping system,
installation of fans and blowers and plumbing fixtures is on development for
Tower 3.


We are pleased to inform you that as of August 15, 2012 The Venice Luxury
Residences overall project accomplishment for Tower’s A and B is 34.75% and
32.70% respectively. For Tower A, concreting is already at 29th floor while
Tower B is already at 28th floor. Installation of mechanical duct, piping of
sanitary and plumbing lines, precast installation of façade, installation of
risers and cross main is ongoing for Tower A. For Tower B, precast
installation of façade, installation of mechanical duct and piping of
sanitary and plumbing lines is ongoing

The project is on progress with accordance to its schedule.









Tuesday, August 10, 2010

The Tuscany Private Estate at McKinley Hill Fort Bonifacio

La Vista Toscana




Tuscany Private Estate at McKinley Hill Fort Bonifacio
Tuscany
Tuscan Feel... 
Ponte Veccio
The Tuscany Private Estate at McKinley Hill Fort Bonifacio