We are pleased to inform you that as of january 15, 2013, Morgan Executive Residences Towers 1,2 and 3 overall accomplishment is 94.61%, 76.40% and 59.20% respectively. For tower 1 ongoing works includes flushing and functionality test of plumbing fixtures at 18th Floor - 22nd Floor (for completion), interior finishing works is on going at 22nd floor with minor finishing works to complete, preparation of BTO for roof deck under mechanical works and ongoing retouching and final painting at basement area. Installation of main door jamb, KED, fixtures, and wires is ongoing for Tower2. For tower 3 on going works includes installation of riser, piping of EWT, waterproofing test of Toilet and Bath at 19th floor and paintinf works.
The project is on progress with accordance to its schedule. |